Woodside completes construction phase for Sangomar field FPSO

29 November 2022


Woodside Energy has completed the construction of a floating production storage and offloading (FPSO) facility for the first phase of Sangomar field development, offshore Senegal.

Named after Senegal’s first president Leopold Sedar Senghor, the FPSO is currently being moved to Keppel Offshore & Marine’s Tuas shipyard in Singapore.

Rendering of the Sangomar Field Development FPSO. (Credit: SOFEC)
Rendering of the Sangomar Field Development FPSO. (Credit: SOFEC)

The vessel is a converted Very Large Crude Carrier with a capacity to produce 100,000 barrels of oil per day.

In Singapore, Keppel will complete the integration of the topsides and support pre-commissioning and commissioning activities for the Leopold Sedar Senghor FPSO.

In 2020, the Australian petroleum exploration and production company Woodside contracted Japanese shipbuilding company MODEC for the supply of the FPSO.

Chinese offshore marine engineering company COSCO Shipping Heavy Industry (Dalian) completed the hull and marine works.

In addition, the Chinese firm completed the works on the external turret, installed topsides module and carried out other conversion work for the FPSO.

BOMESC and COSCO fabricated the topsides modules, while Penglai Jutal Offshore Engineering Heavy Industries (PJOE) built the external turret mooring system.

Woodside Energy CEO Meg O’Neill said: “The Chinese yards achieved excellent safety performance throughout this phase of construction, logging more than 16 million hours of complex construction work without a lost-time injury event.

“The construction teams also successfully navigated the challenges posed by pandemic-related travel and logistical restrictions throughout 2021 and 2022, ensuring the FPSO remained on schedule for start-up at the Sangomar field in late 2023.”

The Phase 1 Sangomar field development is currently around 70% complete. Once operational, it will become the first offshore oil project in Senegal.

In addition to the FPSO, the development also includes 23 wells, and supporting subsea infrastructure. The project is being designed to support tie-in in subsequent phases.

The Phase 1 Sangomar field development is 82% owned by the Woodside, which is also the operator of the project. Senegal’s local oil and gas company PETROSEN holds the remaining 18% stake.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.